DDOT Continues to Drag their Feet

Klingle Road Implementation Strategy

Overview

The week of May 5, 2003, Mayor Williams and the District of Columbia Council agreed to providing funding for reopening Klingle Road as a paved roadway.  In the Fall 2003, DDOT began the process of obtaining Federal Highway Administration (FHWA) and National Park Service (NPS) approvals for this roadway project.  Below is the DDOT Klingle Road Implementation Strategy. 

 

Action

Number of Months to Complete Estimated in
June 2003

Number of Months to Complete Estimated in January 2004

Number of Months to Complete Estimated in September 2004

Preconstruction and Safety improvements; remove hazards

 

2 months

 

8 months

 

9 months

Storm Water Hydrology Analysis


3 months


8 months


1 year, 3 months

Environmental Impact Statement (EIS)


8 months


1 year


1 year, 6 months

Design

9 months

9 months

9 months

Construction

1 year

1 year

1 year

9/27/04


 

For additional information, please email support@repairklingleroad.org